Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
16 Oct 2023 | pipe laying work,grotagging, tank and sump work in progress | Malaparamba RWS Sn - AE | |
07 Oct 2023 | pipe laying work,grotagging, tank and sump work in progress | Malaparamba RWS Sn - AE | |
25 Sep 2023 | pipe laying work,grotagging, tank and sump work in progress | Malaparamba RWS Sn - AE | |
19 Sep 2023 | pipe laying work,grotagging, tank and sump work in progress | Malaparamba RWS Sn - AE | |
08 Sep 2023 | pipe laying work,grotagging, tank and sump work in progress | Malaparamba RWS Sn - AE | |
01 Sep 2023 | pipe laying work,grotagging, tank and sump work in progress | Malaparamba RWS Sn - AE | |
19 Aug 2023 | pipe laying work,grotagging, tank and sump work in progress | Malaparamba RWS Sn - AE | |
11 Aug 2023 | pipe laying work,grotagging, tank and sump work in progress | Malaparamba RWS Sn - AE | |
07 Aug 2023 | pipe laying work,grotagging, tank and sump work in progress | Malaparamba RWS Sn - AE | |
20 Jul 2023 | pipe laying work,grotagging, tank and sump work in progress | Malaparamba RWS Sn - AE |