Status Date |
Overall Project Status |
Project Officer |
Contact |
20 Feb 2024 |
both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR concrete completed. Both tanks plastering and painting work completed. Both tanks stainless steel handrail work completed. 250mm DI 1600m laid, 160mm PE 2700.5m laid, 90mm PE 18500.5m laid, 110mm PE 1500m laid, 140mm PE 1300m laid. 1788 FHTC and 455HTC given.construction of valve chamber started.base slab concreting completed.side wall concreting completed. |
Perinthalmanna AE |
|
17 Feb 2024 |
both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR concrete completed. Both tanks plastering and painting work completed. Both tanks stainless steel handrail work completed. 250mm DI 1600m laid, 160mm PE 2700.5m laid, 90mm PE 18500.5m laid, 110mm PE 1500m laid, 140mm PE 1300m laid. 1788 FHTC and 455HTC given.construction of valve chamber started.base slab concreting completed.side wall concreting completed. |
Perinthalmanna AE |
|
12 Feb 2024 |
both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR concrete completed. Both tanks plastering and painting work completed. Both tanks stainless steel handrail work completed. 250mm DI 1600m laid, 160mm PE 2700.5m laid, 90mm PE 18500.5m laid, 110mm PE 1500m laid, 140mm PE 1300m laid. 1788 FHTC and 455HTC given.construction of valve chamber started.base slab concreting completed.side wall concreting completed. |
Perinthalmanna AE |
|
08 Feb 2024 |
both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR concrete completed. Both tanks plastering and painting work completed. Both tanks stainless steel handrail work completed. 250mm DI 1600m laid, 160mm PE 2700.5m laid, 90mm PE 18500.5m laid, 110mm PE 1500m laid, 140mm PE 1300m laid. 1788 FHTC and 455HTC given.construction of valve chamber started.base slab concreting completed.side wall concreting completed. |
Perinthalmanna AE |
|
07 Feb 2024 |
both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR concrete completed. Both tanks plastering and painting work completed. Both tanks stainless steel handrail work completed. 250mm DI 1600m laid, 160mm PE 2700.5m laid, 90mm PE 18500.5m laid, 110mm PE 1500m laid, 140mm PE 1300m laid. 1774 FHTC and 451HTC given.construction of valve chamber started.base slab concreting completed.side wall concreting completed. |
Perinthalmanna AE |
|
06 Feb 2024 |
both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR concrete completed. Both tanks plastering and painting work completed. Both tanks stainless steel handrail work completed. 250mm DI 1600m laid, 160mm PE 2700.5m laid, 90mm PE 18500.5m laid, 110mm PE 1500m laid, 140mm PE 1300m laid. 1774 FHTC and 451HTC given.construction of valve chamber started.base slab concreting completed.side wall concreting completed. |
Perinthalmanna AE |
|
03 Feb 2024 |
both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR concrete completed. Both tanks plastering and painting work completed. Both tanks stainless steel handrail work completed. 250mm DI 1600m laid, 160mm PE 2700.5m laid, 90mm PE 18500.5m laid, 110mm PE 1500m laid, 140mm PE 1300m laid. 1774 FHTC and 451HTC given.construction of valve chamber started.base slab concreting completed.side wall concreting completed. |
Perinthalmanna AE |
|
30 Jan 2024 |
both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR concrete completed. Both tanks plastering and painting work completed. Both tanks stainless steel handrail work completed. 250mm DI 1600m laid, 160mm PE 2700.5m laid, 90mm PE 18500.5m laid, 110mm PE 1500m laid, 140mm PE 1300m laid. 1747 FHTC and 455HTC given.construction of valve chamber started.base slab concreting completed.side wall concreting completed. |
Perinthalmanna AE |
|
22 Jan 2024 |
both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR concrete completed. Both tanks plastering and painting work completed. Both tanks stainless steel handrail work completed. 250mm DI 1600m laid, 160mm PE 2700.5m laid, 90mm PE 18500.5m laid, 110mm PE 1500m laid, 140mm PE 1300m laid. 1747 FHTC and 455HTC given.construction of valve chamber started.base slab concreting completed.side wall concreting completed. |
Perinthalmanna AE |
|
18 Jan 2024 |
both 8LL Perumbaramb OHSR & 2.25 LL Parakkunnu OHSR concrete completed. Both tanks plastering and painting work completed. Both tanks stainless steel handrail work completed. 250mm DI 1600m laid, 160mm PE 2700.5m laid, 90mm PE 18500.5m laid, 110mm PE 1500m laid, 140mm PE 1300m laid. 1747 FHTC and 455HTC given.construction of valve chamber started.base slab concreting completed.side wall concreting completed. |
Perinthalmanna AE |
|