14 Oct 2024 FHTC work resumed as new applications are were received. Permission from railway received in this office on 24.05.2024. Total 4370 FHTCs effected in this work out of 4045 Payyannur UIDSSMT AE 3
08 Oct 2024 FHTC work resumed as new applications are were received. Permission from railway received in this office on 24.05.2024. Total 4370 FHTCs effected in this work out of 4045 Payyannur UIDSSMT AE 3
04 Oct 2024 FHTC work resumed as new applications are were received. Permission from railway received in this office on 24.05.2024. Total 4370 FHTCs effected in this work out of 4045 Payyannur UIDSSMT AE 3
27 Sep 2024 FHTC work resumed as new applications are were received. Permission from railway received in this office on 24.05.2024. Total 4370 FHTCs effected in this work out of 4045 Payyannur UIDSSMT AE 3
23 Sep 2024 FHTC work resumed as new applications are were received. Permission from railway received in this office on 24.05.2024. Total 4370 FHTCs effected in this work out of 4045 Payyannur UIDSSMT AE 3
18 Sep 2024 FHTC work resumed as new applications are were received. Permission from railway received in this office on 24.05.2024. Total 4370 FHTCs effected in this work out of 4045 Payyannur UIDSSMT AE 3
11 Sep 2024 FHTC work resumed as new applications are were received. Permission from railway received in this office on 24.05.2024. Total 4370 FHTCs effected in this work out of 4045 Payyannur UIDSSMT AE 3
07 Sep 2024 FHTC work resumed as new applications are were received. Permission from railway received in this office on 24.05.2024. Total 4370 FHTCs effected in this work out of 4045 Payyannur UIDSSMT AE 3
02 Sep 2024 FHTC work resumed as new applications are were received. Permission from railway received in this office on 24.05.2024. Total 4370 FHTCs effected in this work out of 4045 Payyannur UIDSSMT AE 3
27 Aug 2024 FHTC work resumed as new applications are were received. Permission from railway received in this office on 24.05.2024. Total 4370 FHTCs effected in this work out of 4045 Payyannur UIDSSMT AE 3