Status Date Overall Project Status Project Officer Contact
06 Aug 2022 Estimate returned for some clarifications and is under scrutiny at Division Kochi JNURM Projects AE-6
11 Jul 2022 Estimate revised under PRICE 3 and under scrutiny at Division Kochi WS Project Dn AE 1
29 Jun 2022 Estimate is being revised to PRICE 3.0 and will be submitted for TS. Kochi WS Project Dn AE 1
15 Jun 2022 Estimate from PWD received, but since there were considerable differences in quantities taken and the items of work when compared with actual site conditions, a letter has been sent to PWD to sort out the issues Kochi WS Project Dn AE 1
18 Apr 2022 Estimate from PWD for cutting sanction not yet received ..Estimate will be submitted for TS after obtaining PWD estimate this week Kochi WS Project Dn AE 1
02 Feb 2022 AS per Proceedings of SE, PH Circle , Kochi 11 No. PHC/CHN/A1/2846/2021 dtd. 10.01.2022, this work has to be transferred to Project Division Kochi 11 Kochi WS Dn EE
28 Jan 2022 AS per Proceedings of SE, PH Circle , Kochi 11 No. PHC/CHN/A1/2846/2021 dtd. 10.01.2022, this work has to be transferred to Project Division Kochi 11 Kochi WS Dn EE
13 Jan 2022 AS per Proceedings of SE, PH Circle , Kochi 11 No. PHC/CHN/A1/2846/2021 dtd. 10.01.2022, this work has to be transferred to Project Division Kochi 11 Kochi WS Dn EE
12 Jan 2022 Estimate submitted to division after correction for issuing TS Thripunithura WS Sn - AE 1
09 Aug 2021 Applied road cutting sanction in PWD portal vide RoW/1012243/16444 dtd.08.08.2021, Estimate under scrutiny in division office awaiting latest rate revision of pipes and specials in PRICE estimate. Kochi WS Dn EE