Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
06 Aug 2022 | Estimate returned for some clarifications and is under scrutiny at Division | Kochi JNURM Projects AE-6 | |
11 Jul 2022 | Estimate revised under PRICE 3 and under scrutiny at Division | Kochi WS Project Dn AE 1 | |
29 Jun 2022 | Estimate is being revised to PRICE 3.0 and will be submitted for TS. | Kochi WS Project Dn AE 1 | |
15 Jun 2022 | Estimate from PWD received, but since there were considerable differences in quantities taken and the items of work when compared with actual site conditions, a letter has been sent to PWD to sort out the issues | Kochi WS Project Dn AE 1 | |
18 Apr 2022 | Estimate from PWD for cutting sanction not yet received ..Estimate will be submitted for TS after obtaining PWD estimate this week | Kochi WS Project Dn AE 1 | |
02 Feb 2022 | AS per Proceedings of SE, PH Circle , Kochi 11 No. PHC/CHN/A1/2846/2021 dtd. 10.01.2022, this work has to be transferred to Project Division Kochi 11 | Kochi WS Dn EE | |
28 Jan 2022 | AS per Proceedings of SE, PH Circle , Kochi 11 No. PHC/CHN/A1/2846/2021 dtd. 10.01.2022, this work has to be transferred to Project Division Kochi 11 | Kochi WS Dn EE | |
13 Jan 2022 | AS per Proceedings of SE, PH Circle , Kochi 11 No. PHC/CHN/A1/2846/2021 dtd. 10.01.2022, this work has to be transferred to Project Division Kochi 11 | Kochi WS Dn EE | |
12 Jan 2022 | Estimate submitted to division after correction for issuing TS | Thripunithura WS Sn - AE 1 | |
09 Aug 2021 | Applied road cutting sanction in PWD portal vide RoW/1012243/16444 dtd.08.08.2021, Estimate under scrutiny in division office awaiting latest rate revision of pipes and specials in PRICE estimate. | Kochi WS Dn EE |