Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
11 Jan 2024 | FHTC work in progress, 640 Nos. connections are completed O | Kondotty AE | |
06 Jan 2024 | FHTC work in progress, 640 Nos. connections are completed | Kondotty AE | |
03 Jan 2024 | FHTC work in progress, 640 Nos. connections are completed | Kondotty AE | |
30 Dec 2023 | FHTC work in progress, 640 Nos. connections are completed | Kondotty AE | |
26 Dec 2023 | FHTC work in progress, 620 Nos. connections are completed | Kondotty AE | |
22 Dec 2023 | FHTC work in progress, 605 Nos. connections are completed | Kondotty AE | |
18 Dec 2023 | FHTC work in progress, 605 Nos. connections are completed | Kondotty AE | |
14 Dec 2023 | FHTC work in progress, 600 nos. connections are completed | Kondotty AE | |
11 Dec 2023 | FHTC work in progress, 600 nos. connections are completed | Kondotty AE | |
05 Dec 2023 | FHTC work in progress, 600 nos. connections are completed | Kondotty AE |