| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 14 Oct 2024 | 100 % of work completed. Measurement submitted for verification | Sasthamcotta WS Sn 1 - AE | |
| 07 Oct 2024 | 85 % of work completed, balance work(pump set supply & erection) work is in progress. | Sasthamcotta WS Sn 1 - AE | |
| 26 Sep 2024 | 85 % of work completed, balance work(pump set supply & erection) work is in progress. | Sasthamcotta WS Sn 1 - AE | |
| 07 Sep 2024 | 85 % of work completed, balance work(pump set supply & erection) is in progress. | Sasthamcotta WS Sn 1 - AE | |
| 04 Sep 2024 | Road restoration work in progress. | Sasthamcotta WS Sn 1 - AE | |
| 02 Sep 2024 | Concrete work in progress at the cutting portion of road | Sasthamcotta WS Sn 1 - AE | |
| 27 Aug 2024 | Laying of 63 , 50 ,32 mm PVC pipe work is in progress. | Sasthamcotta WS Sn 1 - AE | |
| 27 Aug 2024 | Laying of 63 , 50 ,32 mm PVC pipe work is in progress. | Sasthamcotta WS Sn 1 - AE | |
| 21 Aug 2024 | Laying of 63 mm PVC pipe work is in progress. | Sasthamcotta WS Sn 1 - AE | |
| 19 Aug 2024 | Construction of Compound wall work completed, Grill covering to the open well work completed, laying work is in progress. | Sasthamcotta WS Sn 1 - AE |