| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 01 Jan 2023 | Pipe laying work completed | Nedumkandam Sn AE | |
| 01 Sep 2022 | 77% completed, delay due to road cutting permission, joint inspection conducted | Thodupuzha PH Dn EE | |
| 24 Aug 2022 | ongoing | Thodupuzha PH Dn EE | |
| 02 Jul 2022 | Pipe laying towards Chenninaykankudy route completed. Pipe laying towards Parappu from Marykulam town pending at PWD road cutting sanction. Joint inspection with PWD officials and KWA conducted on 24/06/2022. Waiting for estimation. | Nedumkandam Sn AE | |
| 17 Jun 2022 | Agreement Executed on 18.03.2022 | Thodupuzha PH Dn EE | |
| 05 May 2022 | Agreement Executed on 18.03.2022 | Thodupuzha PH Dn EE | |
| 25 Mar 2022 | Agreement Executed on 18.03.2022 | Thodupuzha PH Dn EE | |
| 21 Feb 2022 | Work Tendered | Nedumkandam Sn AE | |
| 10 Jan 2022 | work tendered | Thodupuzha PH Dn EE | |
| 29 Dec 2021 | Estimate under scrutiny | Nedumkandam Sn AE |