Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
06 Feb 2023 | 9,476 m Pipe laid. HTC pipe laying on progress. | Sulthan Bathery PH Sn - AE | |
01 Feb 2023 | 9,476 m Pipe laid. HTC pipe laying on progress. | Sulthan Bathery PH Sn - AE | |
27 Jan 2023 | 9,226 m Pipe laid. HTC pipe laying on progress. | Sulthan Bathery PH Sn - AE | |
23 Jan 2023 | Earthwork excavation on progress | Sulthan Bathery PH Sn - AE | |
16 Jan 2023 | HTC- 20,Pipe laid 9986 meter | Sulthan Bathery PH Sn - AE | |
07 Jan 2023 | Earthwork excavation on progress | Sulthan Bathery PH Sn - AE | |
28 Dec 2022 | Pipe laying work in progress 5165 m completed. | Sulthan Bathery PH Dn EE | |
23 Dec 2022 | Pipe laying work in progress 4,935 m completed. | Sulthan Bathery PH Dn EE | |
16 Dec 2022 | Pipe laying work in progress 5985 m completed. | Sulthan Bathery PH Sn - AE | |
09 Dec 2022 | Pipe laying Work in Progress | Sulthan Bathery PH Dn EE |