Overall Project Status

Status Date Overall Project Status Project Officer Contact
21 Dec 2023 Work in progress- 80640m pipes laid. 1358 FHTCs and 1065 HTC connections given. Sulthan Bathery PH Dn EE
13 Dec 2023 Work in progress- 80640m pipes laid. 1358 FHTCs and 1065 HTC connections given. Sulthan Bathery PH Dn EE
05 Dec 2023 Work in progress- 80640m pipes laid. 1358 FHTCs and 1065 HTC connections given. Sulthan Bathery PH Dn EE
02 Dec 2023 78100 m pipe laid and 2243 HTC Provided. Sulthan Bathery PH Dn EE
24 Nov 2023 78100 m pipe laid and 2243 HTC Provided. Sulthan Bathery PH Dn EE
16 Nov 2023 78100 m pipe laid and 2243 HTC Provided. Sulthan Bathery PH Dn EE
08 Nov 2023 78100 m pipe laid and 2243 HTC Provided. Sulthan Bathery PH Dn EE
30 Oct 2023 992 HTC AND 480 FHTC Provided Sulthan Bathery PH Dn EE
21 Oct 2023 992 HTC AND 480 FHTC Provided Sulthan Bathery PH Dn EE
13 Oct 2023 992 HTC AND 480 FHTC Provided Sulthan Bathery PH Dn EE