Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
27 May 2024 | 147978 mtr PVC pipe supplied out of 295917mtr. 39.334 km PVC pipe laid.100 nos HTC given, work is progressing on.Permission for road cutting placed before DP vide ROW/1098877/108949.2 nd CC part bill submitted.1800 mtrs 200 mm DI pipe supplied. | Kanhangad Proj Dn AE - 1 | |
24 May 2024 | 147978 mtr PVC pipe supplied out of 295917mtr. 39.334 mtr PVC pipe laid.100 nos HTC given, work is progressing on.Permission for road cutting placed before DP vide ROW/1098877/108949.2 nd CC part bill submitted.1800 mtrs 200 mm DI pipe supplied. | Kanhangad Proj Dn AE - 1 | |
15 May 2024 | 147978 mtr PVC pipe supplied out of 295917mtr. 36112 mtr PVC pipe laid.100 nos HTC given, work is progressing on.Permission for road cutting placed before DP vide ROW/1098877/108949. | Kanhangad Proj Dn AE - 1 | |
14 May 2024 | 147978 mtr PVC pipe supplied out of 295917mtr. 36035 mtr PVC pipe laid.100 nos HTC given, work is progressing on.Permission for road cutting placed before DP vide ROW/1098877/108949. | Kanhangad Proj Dn AE - 1 | |
09 May 2024 | 147978 mtr PVC pipe supplied out of 295917mtr. 36035 mtr PVC pipe laid.100 nos HTC given, work is progressing on.Permission for road cutting placed before District Panchayath vide ROW/1098877/108949. | Kanhangad Proj Dn AE - 1 | |
03 May 2024 | 147978 mtr PVC pipe supplied out of 295917mtr. 30 km PVC pipe laid. work is progressing on.Permission for road cutting placed before DP vide ROW/1098877/108949. | Kanhangad Proj Dn AE - 1 | |
03 May 2024 | 147978 mtr PVC pipe supplied out of 295917mtr. 27.313 km PVC pipe laid. work is progressing on.Permission for road cutting placed before DP vide ROW/1098877/108949. | Kanhangad Proj Dn AE - 1 | |
24 Apr 2024 | 147978 mtr PVC pipe supplied out of 295917mtr. 27.313 km PVC pipe laid. work is progressing on.Permission for road cutting placed before DP vide ROW/1098877/108949. | Kanhangad Proj Dn AE - 1 | |
23 Apr 2024 | 147978 mtr PVC pipe supplied out of 295917mtr. 10 km PVC pipe laid. work is progressing on.Permission for road cutting placed before DP vide ROW/1098877/108949. | Kanhangad Proj Dn AE - 1 | |
17 Apr 2024 | 147978 mtr PVC pipe supplied out of 295917mtr. 10 km PVC pipe laid. work is progressing on.Permission for road cutting placed before DP vide ROW/1098877/108949. | Kanhangad Proj Dn AE - 1 |