10 Mar 2025 700 mm DI Pipe 709 nos (3899.5 m) supplied. Bill submitted field updation - 86276438/- Changanaserry PH Sn - AE
02 Mar 2025 700 mm DI Pipe 709 nos (3899.5 m) supplied. Bill submitted field updation - 86276438/- Changanaserry PH Sn - AE
27 Feb 2025 700 mm DI Pipe 709 nos (3899.5 m) supplied. Bill submitted field updation - 86276438/- Changanaserry PH Sn - AE
22 Feb 2025 700 mm DI Pipe 709 nos (3899.5 m) supplied. Bill submitted field updation - 86276438/- Changanaserry PH Sn - AE
16 Feb 2025 700 mm DI Pipe 709 nos (3899.5 m) supplied. Bill submitted field updation - 86276438/- Changanaserry PH Sn - AE
09 Feb 2025 700 mm DI Pipe 709 nos (3899.5 m) supplied. Bill submitted field updation - 86276438/- Changanaserry PH Sn - AE
26 Jan 2025 700 mm DI Pipe 709 nos (3899.5 m) supplied. Bill submitted field updation - 86276438/- Changanaserry PH Sn - AE
16 Jan 2025 700 mm DI Pipe 709 nos (3899.5 m) supplied. Bill submitted field updation - 86276438/- Changanaserry PH Sn - AE
12 Jan 2025 700 mm DI Pipe 709 nos (3899.5 m) supplied. Bill submitted field updation - 86276438/- Changanaserry PH Sn - AE
03 Jan 2025 700 mm DI Pipe 709 nos (3899.5 m) supplied. Bill submitted field updation - 86276438/- Changanaserry PH Sn - AE