Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
06 Apr 2024 | 95% work completed.5165m pipe laid.44nos. FHTC provided | Perlassery Sn 2 AE | |
27 Mar 2024 | work in progress | Perlassery Sn 2 AE | |
18 Mar 2024 | work in progress | Perlassery Sn 2 AE | |
11 Mar 2024 | work in progress | Perlassery Sn 2 AE | |
28 Feb 2024 | AGREEMENT EXECUTED ON 19.01.2024,Pipe have been supplied | Perlassery Sn 2 AE | |
14 Feb 2024 | AGREEMENT EXECUTED ON 19.01.2024 | Perlassery Sn 2 AE | |
06 Feb 2024 | AGREEMENT EXECUTED ON 19.01.2024 | Perlassery Sn 2 AE | |
29 Jan 2024 | AGREEMENT EXECUTED ON 19.01.2024 | Perlassery Sn 2 AE | |
19 Jan 2024 | AGREEMENT EXECUTED ON 19.01.2024 | Kannur PH Dn EE | |
08 Jan 2024 | WORK ORDER ISSUED ON 08.01.2024 | Kannur PH Dn EE |