Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
02 Nov 2023 | Pothanicad panchayath Package II -8 % completed .Design of of tank completed ,pipe laying 30 km completed. konnanpara tank work in progress, floor slab | Piravam Project Sub Dn AE 2 | |
07 Sep 2023 | Pothanicad panchayath Package II -5% completed ,design of of tank completed ,pipe laying 16 km completed | Piravam Project Sub Dn AE 2 | |
24 Aug 2023 | Pothanicad panchayath Package II -5% completed ,design of of tank completed ,pipe laying 16 km completed | Piravam Project Sub Dn AE 2 | |
06 Jul 2023 | 300 mm DI line laid,Work of CWPM from Pulinthanam tank and PVC distribution line in progress | Piravam Project Sub Dn AE 2 | |
30 Jun 2023 | 300 mm DI line laid,Work of CWPM from Pulinthanam tank and PVC distribution line in progress | Piravam Project Sub Dn AE 2 | |
27 Jun 2023 | 300 mm DI line laid,Work of CWPM from Pulinthanam tank and PVC distribution line in progress | Piravam Project Sub Dn AE 2 | |
22 Jun 2023 | 300 mm DI line laid,Work of CWPM from Pulinthanam tank and PVC distribution line in progress | Piravam Project Sub Dn AE 2 | |
09 Jun 2023 | 300 mm DI line laid,Work of CWPM from Pulinthanam tank and PVC distribution line in progress | Piravom Project Sub Dn AEE | |
08 Jun 2023 | 300 mm DI line laid,Work of CWPM from Pulinthanam tank and PVC distribution line in progress | Piravam Project Sub Dn AE 2 | |
06 Jun 2023 | pipe laying in progress | Piravam Project Sub Dn AE 2 |