Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
13 Dec 2022 | 64 FHTC given. 3220.7m 250mm DI laid. 160mm PE 2775m laid | Perinthalmanna AE | |
29 Nov 2022 | 57 FHTC given. 302.5m 250mm DI laid. 160mm PE 500m laid | Perinthalmanna AE | |
25 Nov 2022 | 50 FHTC given. 302.5m 250mm DI laid. 160mm PE 500m laid | Perinthalmanna AE | |
17 Nov 2022 | 25 FHTC given. 302.5m 250mm DI laid. 160mm PE 500m laid. | Perinthalmanna AE | |
15 Nov 2022 | 18 FHTC given. 302.5m 250mm DI laid. | Perinthalmanna AE | |
14 Nov 2022 | 17 FHTC given. 302.5m 250mm DI laid. | Perinthalmanna AE | |
09 Nov 2022 | 16 FHTC given. 302.5m 250mm DI laid. | Perinthalmanna AE | |
05 Nov 2022 | 5 FHTC given. 302.5m 250mm DI laid. | Perinthalmanna AE | |
18 Oct 2022 | CC 3rd and part bill submitted, Amount-32160128. List of connection to be given is obtained from Panchayath office | Perinthalmanna AE | |
15 Oct 2022 | CC 3rd and part bill submitted, Amount-32160128. List of connection to be given is obtained from Panchayath office | Perinthalmanna AE |