Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
11 Nov 2021 | Estimate returned from Division for correction and revision as directed is under progress | Trippunithura WS Sn - AE 2 | |
06 Nov 2021 | Estimate returned from Division for correction and revision as directed is under progress | Trippunithura WS Sn - AE 2 | |
03 Nov 2021 | Estimate returned from Division for correction and revision as directed is under progress | Trippunithura WS Sn - AE 2 | |
28 Oct 2021 | Estimate forwarded to SE for approval | Trippunithura WS Sn - AE 2 | |
25 Oct 2021 | Estimate forwarded to SE for approval | Trippunithura WS Sn - AE 2 | |
22 Oct 2021 | Estimate forwarded to SE for approval | Trippunithura WS Sn - AE 2 | |
21 Oct 2021 | Estimate forwarded to SE for approval | Trippunithura WS Sn - AE 2 | |
12 Oct 2021 | Estimate forwarded to SE for approval | Trippunithura WS Sn - AE 2 | |
04 Oct 2021 | Estimate forwarded to SE for approval | Trippunithura WS Sn - AE 2 | |
24 Sep 2021 | Estimate forwarded to SE for approval | Kochi WS Dn EE |