- Home
- KIIFB - Project WRD005-125- Replacement...
KIIFB - Project WRD005-125- Replacement of Transmission Main Kochi PH circle - Project 11 Improvements of water supply to Thripunithura municipality (East fort Jn. to market - Puthiyakavu Ayurveda Jn.)Est. No. 2018/10889
Project |
KIIFB - Project WRD005-125- Replacement of Transmission Main Kochi PH circle - Project 11 Improvements of water supply to Thripunithura municipality (East fort Jn. to market - Puthiyakavu Ayurveda Jn.)Est. No. 2018/10889 |
Project Code |
EKMKIIFB04217907 |
Type |
Main project |
Funding Agency |
KIIFB |
Category |
KIIFB |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
KIIFB - Project WRD005-125- Replacement of Transmission Main Kochi PH circle - Project 11 Improvements of water supply to Thripunithura municipality (East fort Jn. to market - Puthiyakavu Ayurveda Jn.) Est. No. 2018/10889 |
Status |
Dropped |
District |
Ernakulam |
Executing Office |
Kochi Project Division |
AS Amount (Rs) |
22129520
|
AS Number |
WRD005-125/APR-6/2021/KIIFB |
TS Amount (Rs) |
0 |
TS Number |
00 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
5000 |
Capacity in MLD |
16.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Thripunithura municipality |
Packages
No. |
Project Name |
Location |
View |
1 |
KIIFB - Project WRD005-125- Replacement of Transmission Main Kochi PH circle - Project 11 Improvements of water supply to Thripunithura municipality (East fort Jn. to market - Puthiyakavu Ayurveda Jn.)Est. No. 2018/10889 |
Kochi Project Division |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
06 Aug 2022 |
Estimate revised to 310 Lakhs, revised AS proposal submitted. narrow road under DLP, PWD rejected application. JJM Udayamperoor pumping main to pass through the same road. This work can be arranged along with JJM work after DLP
|
Kochi JNURM Projects AE-6 |
|
01 Aug 2022 |
Estimate revised to 310 Lakhs, revised AS proposal submitted. narrow road under DLP, PWD rejected application. JJM Udayamperoor pumping main to pass through the same road. This work can be arranged along with JJM work after DLP. |
Kochi WS Project Dn EE |
|
11 Jul 2022 |
Estimate recasted under PRICE 3 and under scrutiny at Division |
Kochi WS Project Dn AE 1 |
|
29 Jun 2022 |
Estimate created under PRICE 3.0 and is under scrutiny at Division |
Kochi WS Project Dn AE 1 |
|
15 Jun 2022 |
Application to HO for submitting in e samiksha for resolving the rejection of road cutting permission by PWD |
Kochi WS Project Dn AE 1 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
Date is not specified |
Scheduled date of Completion of the Project |
Date is not specified |
Expected date of Completion |
31/08/2022 |