Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
31 Jan 2024 90 mm PVC laid out of 15000 meter PVC pipe to be laid 5321.5 meter laying has been completed. Alappuzha Project Dn PM
15 Jan 2024 90 mm PVC laid out of 15000 meter PVC pipe to be laid 5020 meter laying has been completed. Alappuzha Project Dn PM
04 Jan 2024 90 mm PVC laid out of 15000 meter PVC pipe to be laid 4680 meter laying has been completed. Alappuzha Project Dn PM
15 Dec 2023 90 mm PVC laid out of 15000 meter PVC pipe to be laid 910 meter laying has been completed. Alappuzha Project Dn PM
04 Dec 2023 Work start on 04.12.2023 Alappuzha Project Dn PM