Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
31 Jan 2024 | 90 mm PVC laid out of 15000 meter PVC pipe to be laid 5321.5 meter laying has been completed. | Alappuzha Project Dn PM | |
15 Jan 2024 | 90 mm PVC laid out of 15000 meter PVC pipe to be laid 5020 meter laying has been completed. | Alappuzha Project Dn PM | |
04 Jan 2024 | 90 mm PVC laid out of 15000 meter PVC pipe to be laid 4680 meter laying has been completed. | Alappuzha Project Dn PM | |
15 Dec 2023 | 90 mm PVC laid out of 15000 meter PVC pipe to be laid 910 meter laying has been completed. | Alappuzha Project Dn PM | |
04 Dec 2023 | Work start on 04.12.2023 | Alappuzha Project Dn PM |