| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 31 Dec 2024 | BILL UNDER PREPARATION | Kottakkal PH Sn AE | |
| 21 Oct 2024 | WORK COMPLETED | Kottakkal PH Sn AE | |
| 08 Oct 2024 | Laying completed 1608 m PVC Includes (90 MM & 75 MM ) Balance work : Restoration of PWD road of 120 m | Kottakkal PH Sn AE | |
| 28 Sep 2024 | Laying completed 1608 m PVC Includes (90 MM & 75 MM ) Balance work : Restoration of PWD road of 120 m | Kottakkal PH Sn AE | |
| 26 Sep 2024 | Laying completed 1608 m PVC Includes (90 MM & 75 MM ) Balance work : Restoration of PWD road of 120 m | Kottakkal PH Sn AE | |
| 19 Sep 2024 | work in progress | Kottakkal PH Sn AE | |
| 14 Aug 2024 | 90 mm pvc - 114 length pipe completed 75 mm pvc -161 lenght pipe completd 65 mm GI - 7 lenghth pipe completed | Kottakkal PH Sn AE | |
| 30 Jul 2024 | ON GOING | Kottakkal PH Sn AE | |
| 26 Jul 2024 | ONGOING | Kottakkal PH Sn AE | |
| 05 Jul 2024 | work ongoing | Kottakkal PH Sn AE |