Overall Project Status

Status Date Overall Project Status Project Officer Contact
05 Aug 2024 20 % completed, 957m pipe laid, 65 nos alterations are given. Heavy rain affected the progress of work. Kollam WS Sn 1 - AE
01 Aug 2024 20 % completed, 957m pipe laid, 65 nos alterations are given. Heavy rain affected the progress of work. Kollam WS Sn 1 - AE
29 Jul 2024 20 % completed, 957m pipe laid, 65 nos alterations are given. Heavy rain affected the progress of work. Kollam WS Sn 1 - AE
25 Jul 2024 20 % completed, 957m pipe laid, 65 nos alterations are given. Heavy rain affected the progress of work. Kollam WS Sn 1 - AE
22 Jul 2024 20 % completed, 957m pipe laid, 65 nos alterations are given. Heavy rain affected the progress of work. Kollam WS Sn 1 - AE
18 Jul 2024 20 % completed, 957m pipe laid, 65 nos alterations are given. Heavy rain affected the progress of work. Kollam WS Sn 1 - AE
15 Jul 2024 20 % completed, 957m pipe laid, 65 nos alterations are given. Heavy rain affected the progress of work. Kollam WS Sn 1 - AE
15 Jul 2024 20 % completed, 957m pipe laid, 65 nos alterations are given. Heavy rain affected the progress of work. Kollam WS Sn 1 - AE
09 Jul 2024 20 % completed, 957m pipe laid, 65 nos alterations are given. Heavy rain affected the progress of work. Kollam WS Sn 1 - AE
06 Jul 2024 20 % completed, 957m pipe laid, 65 nos alterations are given. Heavy rain affected the progress of work. Kollam WS Sn 1 - AE