| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 04 Sep 2024 | 22 % completed, 1019 m pipe laid, 126 nos alterations are given. | Kollam WS Sn 1 - AE | |
| 31 Aug 2024 | 22 % completed, 1019 m pipe laid, 126 nos alterations are given. | Kollam WS Sn 1 - AE | |
| 30 Aug 2024 | 22 % completed, 1019 m pipe laid, 126 nos alterations are given. | Kollam WS Sn 1 - AE | |
| 27 Aug 2024 | 22 % completed, 1019 m pipe laid, 126 nos alterations are given. | Kollam WS Sn 1 - AE | |
| 22 Aug 2024 | 22 % completed, 1019 m pipe laid, 126 nos alterations are given. | Kollam WS Sn 1 - AE | |
| 19 Aug 2024 | 22 % completed, 1019 m pipe laid, 126 nos alterations are given. | Kollam WS Sn 1 - AE | |
| 16 Aug 2024 | 20 % completed, 957m pipe laid, 65 nos alterations are given. | Kollam WS Sn 1 - AE | |
| 12 Aug 2024 | 20 % completed, 957m pipe laid, 65 nos alterations are given. Heavy rain affected the progress of work. | Kollam WS Sn 1 - AE | |
| 09 Aug 2024 | 20 % completed, 957m pipe laid, 65 nos alterations are given. Heavy rain affected the progress of work. | Kollam WS Sn 1 - AE | |
| 07 Aug 2024 | 20 % completed, 957m pipe laid, 65 nos alterations are given. Heavy rain affected the progress of work. | Kollam WS Sn 1 - AE |