| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 07 Aug 2023 | Revised AS WRD005-127/APR-6/2023/KIIFB got on 24-04-2023,TS Estimate submitted on 17/05/2023 | Mathilakam AE | |
| 03 Aug 2023 | Revised AS WRD005-127/APR-6/2023/KIIFB got on 24-04-2023,TS Estimate submitted on 17/05/2023 | Vadanappilly AE | |
| 31 Jul 2023 | Revised AS WRD005-127/APR-6/2023/KIIFB got on 24-04-2023,TS Estimate submitted on 17/05/2023 | Mathilakam AE | |
| 27 Jul 2023 | Revised AS WRD005-127/APR-6/2023/KIIFB got on 24-04-2023,TS Estimate submitted on 17/05/2023 | Vadanappilly AE | |
| 24 Jul 2023 | Revised AS WRD005-127/APR-6/2023/KIIFB got on 24-04-2023,TS Estimate submitted on 17/05/2023 | Mathilakam AE | |
| 24 Jul 2023 | Revised AS WRD005-127/APR-6/2023/KIIFB got on 24-04-2023,TS Estimate submitted on 17/05/2023 | Vadanappilly AE | |
| 20 Jul 2023 | Revised AS WRD005-127/APR-6/2023/KIIFB got on 24-04-2023,TS Estimate submitted on 17/05/2023 | Vadanappilly AE | |
| 20 Jul 2023 | Revised AS WRD005-127/APR-6/2023/KIIFB got on 24-04-2023,TS Estimate submitted on 17/05/2023 | Mathilakam AE | |
| 18 Jul 2023 | Revised AS WRD005-127/APR-6/2023/KIIFB got on 24-04-2023,TS Estimate submitted on 17/05/2023 | Vadanappilly AE | |
| 13 Jul 2023 | Revised AS WRD005-127/APR-6/2023/KIIFB got on 24-04-2023,TS Estimate submitted on 17/05/2023 | Mathilakam AE |