31 May 2021 Projects I to V Revised estimate submitted for revised AS. Project VI 600 mm DI pipe supplied. Irinjalakkuda PH Dn EE
23 May 2021 Projects I to V Revised estimate submitted for revised AS. Project VI 600 mm DI pipe supplied. Irinjalakkuda PH Dn EE
17 May 2021 Projects I to V Revised estimate submitted for revised AS. Project VI 600 mm DI pipe supplied. Irinjalakkuda PH Dn EE
30 Apr 2021 Projects I to V Revised estimate submitted for revised AS. Project VI 600 mm DI pipe supplied. Irinjalakkuda PH Dn EE
22 Apr 2021 Part VI- 600 mm DI pipe supplied. Irinjalakkuda PH Dn EE
16 Mar 2021 Projects I to V Revised estimate submitted for revised AS. Project VI Agreement executed, work not started. Irinjalakkuda PH Dn EE
06 Feb 2021 Agreement executed . Irinjalakkuda PH Dn EE
28 Jan 2021 Project-VI-Agreement Executed-Due to delay in getting Pipe from manufacturer, contractor has not supplied DI Pipes Irinjalakkuda PH Dn EE
28 Jan 2021 Project-V-Submitted for Revised AS Irinjalakkuda PH Dn EE
28 Jan 2021 Project-IV-Submitted for Revised AS Irinjalakkuda PH Dn EE