Overall Project Status

Status Date Overall Project Status Project Officer Contact
20 Aug 2022 KIIFB - Package I,III, V - Esimate in Price 3. is submitted for Revised AS Chalakudy AE 1
05 Aug 2022 KIIFB - Package I,III, V - Esimate in Price 3. is submitted for Revised AS Chalakudy AE 1
03 Aug 2022 Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval.Revised DER submitted for approval on 26-02-2022. Package VI contractor filed a case. Work cancelled and tender invited under risk and cost of the contractor. Due to high rate (50% above as per DSOR 2016 and 25% above as per DSOR 2018), the above re tender also cancelled and revised DER submitted for revised AS on 22-06-22. Now estimate is revised in PRICE 3 Mathilakam AE
01 Aug 2022 Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval.Revised DER submitted for approval on 26-02-2022. Package VI contractor filed a case. Work cancelled and tender invited under risk and cost of the contractor. Due to high rate (50% above as per DSOR 2016 and 25% above as per DSOR 2018), the above re tender also cancelled and revised DER submitted for revised AS on 22-06-22. Now estimate is revised in PRICE 3 Irinjalakkuda PH Dn EE
01 Aug 2022 Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval.Revised DER submitted for approval on 26-02-2022. Package VI contractor filed a case. Work cancelled and tender invited under risk and cost of the contractor. Due to high rate (50% above as per DSOR 2016 and 25% above as per DSOR 2018), the above re tender also cancelled and revised DER submitted for revised AS on 22-06-22. Now estimate is revised in PRICE 3 Irinjalakkuda PH Dn EE
26 Jul 2022 Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval.Revised DER submitted for approval on 26-02-2022. Package VI contractor filed a case. Work cancelled and tender invited under risk and cost of the contractor. Due to high rate (50% above as per DSOR 2016 and 25% above as per DSOR 2018), the above re tender also cancelled and revised DER submitted for revised AS on 22-06-22 Mathilakam AE
19 Jul 2022 Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval.Revised DER submitted for approval on 26-02-2022. Package VI contractor filed a case. Work cancelled and tender invited under risk and cost of the contractor. Due to high rate (50% above as per DSOR 2016 and 25% above as per DSOR 2018), the above re tender also cancelled and revised DER submitted for revised AS on 22-06-22 Mathilakam AE
18 Jul 2022 Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval.Revised DER submitted for approval on 26-02-2022. Package VI contractor filed a case. Work cancelled and tender invited under risk and cost of the contractor. Due to high rate (50% above as per DSOR 2016 and 25% above as per DSOR 2018), the above re tender also cancelled and revised DER submitted for revised AS on 22-06-22 Mathilakam AE
14 Jul 2022 Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval.Revised DER submitted for approval on 26-02-2022. Package VI contractor filed a case. Work cancelled and tender invited under risk and cost of the contractor. Due to high rate (50% above as per DSOR 2016 and 25% above as per DSOR 2018), the above re tender also cancelled and revised DER submitted for revised AS on 22-06-22 Mathilakam AE
11 Jul 2022 Packaged I to V , Revised estimate for revised AS (revised as directed by KIIFB after joint inspection conducted on 17-4-21) submitted for approval.Revised DER submitted for approval on 26-02-2022. Package VI contractor filed a case. Work cancelled and tender invited under risk and cost of the contractor. Due to high rate (50% above as per DSOR 2016 and 25% above as per DSOR 2018), the above re tender also cancelled and revised DER submitted for revised AS on 22-06-22 Irinjalakkuda PH Dn EE