Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
15 Sep 2021 | On 13th August 2021, Asst. Executive Engineer presided online meeting with all the 21 ward members along with Panchayath President and Secretary at Panchayath Office | Kollam Project HD | |
15 Sep 2021 | On 10th August 2021, instruction received from Kottamkara Panchayath officials to stop ongoing JJM connection works in wards where other private water connections projects were currently done | Kollam Project HD | |
15 Sep 2021 | Work started on 26 July 2021. | Kollam Project HD | |
19 Jul 2021 | Agreement executed but the entire Panchayat is in triple lockdown...so no work in progress | Kollam Project HD | |
01 Jul 2021 | Agreement executed but the entire Panchayat is in triple lockdown...so no work in progress | Kollam Project HD | |
23 Jun 2021 | Agreement executed but the entire Panchayat is in triple lockdown...so no work in progress | Kollam Project HD | |
14 Jun 2021 | Agreement executed but the entire Panchayat is in triple lockdown...so no work in progress | Kollam Project HD | |
10 Jun 2021 | AGREEMENT EXECUTED | Kollam Project HD | |
09 Jun 2021 | AGREEMENT EXECUTED | Kollam Project HD | |
08 Jun 2021 | AGREEMENT EXECUTED | Kollam Project HD |