Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
28 Jun 2024 | Work in progress, Total pipe tobe laid 125km, Total pipe laid 37km, Dt of Completion 13.05.2024. EOT requested up to 13.10.2024 | Kanhangad Proj Dn AE - 2 | |
26 Jun 2024 | Work in progress, Total pipe tobe laid 125km, Total pipe laid 37km, Dt of Completion 13.05.2024. EOT requested up to 13.10.2024 | Kanhangad Proj Dn AE - 2 | |
24 Jun 2024 | Work in progress, Total pipe tobe laid 125km, Total pipe laid 37km, Dt of Completion 13.05.2024. EOT requested up to 13.10.2024 | Kanhangad Proj Dn AE - 2 | |
21 Jun 2024 | Work in progress. 37 km of pipeline laid | Kanhangad Proj Dn AE - 2 | |
19 Jun 2024 | Work in progress. 37 km of pipeline laid | Kanhangad Proj Dn AE - 2 | |
17 Jun 2024 | Work in progress. 37 km of pipeline laid | Kanhangad Proj Dn AE - 2 | |
14 Jun 2024 | Work in progress. 37 km of pipeline laid | Kanhangad Proj Dn AE - 2 | |
12 Jun 2024 | Work in progress. 37 km of pipeline laid | Kanhangad Proj Dn AE - 2 | |
10 Jun 2024 | Work in progress. 37 km of pipeline laid | Kanhangad Proj Dn AE - 2 | |
07 Jun 2024 | Work in progress. 37 km of pipeline laid | Kanhangad Proj Dn AE - 2 |