Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
29 Aug 2021 | Work in progress | 5% Completed | 29/08/2021 90mm pvc pipe 6 kg-6.58km laid | Chittur Project Dn - AE 2 | |
28 Aug 2021 | Work in progress | 5% Completed | 28/08/2021 90mm pvc pipe 6 kg-6.58km laid | Chittur Project Dn - AE 2 | |
17 Aug 2021 | Work in progress | 3% Completed | 17/08/2021 90mm pvc pipe 6 kg-5598.00m laid | Chittur Project Dn - AE 2 | |
16 Aug 2021 | Work in progress | 2% Completed | 16/08/2021 90mm pvc pipe 6 kg-3500m laid | Chittur Project Dn - AE 2 | |
12 Aug 2021 | Work in progress | 1% Completed | 12/08/2021 90mm pvc pipe 6 kg-3000m laid | Chittur Project Dn - AE 2 | |
09 Aug 2021 | Work in progress | 1% Completed | 09/08/2021 90mm pvc pipe 6 kg-481.00 m laid | Chittur Project Dn - AE 2 | |
01 Aug 2021 | Not Started | 01/08/2021 Supply order for pipes given. Third party inspection to be completed | Chittur Project Dn - AE 2 | |
27 Jul 2021 | Not Started | 27/07/2021 Supply order for pipes given. Third party inspection to be completed | Chittur Project Dn - AE 2 | |
24 Jul 2021 | Not Started | 24/07/2021 Supply order for pipes given. Third party inspection to be completed | Chittur Project Dn - AE 2 | |
19 Jul 2021 | Not Started | 19/07/2021 Supply order for pipes given. Third party inspection to be completed | Chittur Project Dn - AE 2 |