Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
14 Feb 2023 | Newly installed pump is not running successfully. So informed contractor to change the pumpset and letter given to him | Areacode AE | |
14 Feb 2023 | Awaiting response from KSEB for running newly installed pump | Areacode AE | |
02 Feb 2023 | Awaiting response from KSEB for running newly installed pump | Areacode AE | |
18 Jan 2023 | Awaiting response from KSEB for running newly installed pump | Areacode AE | |
10 Jan 2023 | Awaiting response from KSEB for running newly installed pump | Areacode AE | |
05 Jan 2023 | One 125 HP pump set is installed and awaiting proper measures from KSEB for running the pump. Regarding FHTCs- Out of 2084 applications received from panchayath, 1958 connections had given. And of balance 126 connections, 35 have given as HTC and rest is continuing. Letters were send to Panchayath for giving balance applications on 24/11/22 and 16/12/22 and no response obtained. | Areacode AE | |
29 Dec 2022 | One 125 HP pump set is installed and awaiting proper measures from KSEB for running the pump. Regarding FHTCs- Out of 2084 applications received from panchayath, 1958 connections had given. And of balance 126 connections, 35 have given as HTC and rest is continuing. Letters were send to Panchayath for giving balance applications on 24/11/22 and 16/12/22 and no response obtained. | Areacode AE | |
27 Dec 2022 | FHTC's in progress. Motor installed and pump going to install. Transformer changed and cables and wires to be replaced by KSEB for proper working of pumps | Areacode AE | |
19 Dec 2022 | FHTC's in progress. Motor installed and pump going to install. Transformer changed and cables and wires to be replaced by KSEB for proper working of pumps | Areacode AE | |
12 Dec 2022 | FHTC's in progress. Motor installed and pump going to install. Transformer changed and cables and wires to be replaced by KSEB for proper working of pumps | Areacode AE |