Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
30 Sep 2022 | Pipe line extension work and FHTCs in progress | Areacode AE | |
26 Sep 2022 | Pipe line extension work and FHTCs in progress | Areacode AE | |
16 Sep 2022 | Pipe line extension work and FHTCs in progress | Areacode AE | |
12 Sep 2022 | Pipe line extension work and FHTCs in progress | Areacode AE | |
06 Sep 2022 | Pipe line extension work and FHTCs in progress | Areacode AE | |
28 Aug 2022 | Pipe line extension work and FHTCs in progress | Areacode AE | |
23 Aug 2022 | Pipe line extension work and FHTCs in progress | Areacode AE | |
22 Aug 2022 | Pipe line extension work and FHTCs in progress | Areacode AE | |
17 Aug 2022 | Pipe line extension work and FHTCs in progress | Areacode AE | |
10 Aug 2022 | Pipe line extension work and FHTCs in progress | Areacode AE |