Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
01 May 2023 | Tile restoration work at Ward 4 on progress. | Kochi JNURM Projects AE-6 | |
25 Apr 2023 | Road restoration work (Ward - 4) Pixel house Graphic Design, KSEB post No. V/PO/33/1 | Kochi JNURM Projects AE-6 | |
12 Apr 2023 | Road restoration work (Ward 4) KSEB post No. V/PO/23/6 Branch Road Puthanpally Adichilikkadav Road | Kochi JNURM Projects AE-6 | |
30 Mar 2023 | Total connection given - 1233 Nos. | Kochi JNURM Projects AE-6 | |
27 Mar 2023 | Total connection given - 1225 Nos. | Kochi JNURM Projects AE-6 | |
16 Mar 2023 | Total connection given - 1224 nos. | Kochi JNURM Projects AE-6 | |
08 Mar 2023 | Total connection given - 1214 nos. | Kochi JNURM Projects AE-6 | |
03 Mar 2023 | Total connection given - 1210 Nos. | Kochi JNURM Projects AE-6 | |
28 Feb 2023 | Total connection given - 1202 Nos. | Kochi JNURM Projects AE-6 | |
23 Feb 2023 | Total connection supplied - 1190 Nos. | Kochi JNURM Projects AE-6 |