Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
01 May 2023 Tile restoration work at Ward 4 on progress. Kochi JNURM Projects AE-6
25 Apr 2023 Road restoration work (Ward - 4) Pixel house Graphic Design, KSEB post No. V/PO/33/1 Kochi JNURM Projects AE-6
12 Apr 2023 Road restoration work (Ward 4) KSEB post No. V/PO/23/6 Branch Road Puthanpally Adichilikkadav Road Kochi JNURM Projects AE-6
30 Mar 2023 Total connection given - 1233 Nos. Kochi JNURM Projects AE-6
27 Mar 2023 Total connection given - 1225 Nos. Kochi JNURM Projects AE-6
16 Mar 2023 Total connection given - 1224 nos. Kochi JNURM Projects AE-6
08 Mar 2023 Total connection given - 1214 nos. Kochi JNURM Projects AE-6
03 Mar 2023 Total connection given - 1210 Nos. Kochi JNURM Projects AE-6
28 Feb 2023 Total connection given - 1202 Nos. Kochi JNURM Projects AE-6
23 Feb 2023 Total connection supplied - 1190 Nos. Kochi JNURM Projects AE-6