| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 16 Aug 2025 | Providing house connections | Kadakkal PH Sn - AE | |
| 28 Jul 2025 | Work is in final stage of completion | Kadakkal PH Sn - AE | |
| 12 Jun 2025 | Painting work of old sump building | Kadakkal PH Sn - AE | |
| 05 Jun 2025 | Truss work completed | Kadakkal PH Sn - AE | |
| 26 May 2025 | Truss work and maintenance of existing pumphouse at Veykkal | Kadakkal PH Sn - AE | |
| 17 May 2025 | Roof slab concreting | Kadakkal PH Sn - AE | |
| 14 May 2025 | Sump Roof slab reinforcement | Kadakkal PH Sn - AE | |
| 07 May 2025 | Side wall concreting of veikkal sump | Kadakkal PH Sn - AE | |
| 02 May 2025 | Side wall shuttering of sump | Kadakkal PH Sn - AE | |
| 02 Apr 2025 | Concreting of 1/3rd side wall of sump | Kadakkal PH Sn - AE |