| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 06 Nov 2024 | Same Status | Kadakkal PH Sn - AE | |
| 01 Nov 2024 | Same Status | Kadakkal PH Sn - AE | |
| 29 Oct 2024 | same status | Kadakkal PH Sn - AE | |
| 16 Oct 2024 | Chamber work progressing | Kadakkal PH Sn - AE | |
| 11 Oct 2024 | Chamber concreting | Kadakkal PH Sn - AE | |
| 10 Oct 2024 | Earth excavation for chamber @Nilamel to Kuriyod road | Kadakkal PH Sn - AE | |
| 06 Oct 2024 | Side wall concreting for chamber near Nilamel panchayath | Kadakkal PH Sn - AE | |
| 06 Oct 2024 | Shuttering and reinforcement work | Kadakkal PH Sn - AE | |
| 05 Oct 2024 | Chamber PCC work | Kadakkal PH Sn - AE | |
| 04 Oct 2024 | Earthwork excavation for chamber | Kadakkal PH Sn - AE |