| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 20 Feb 2025 | Procurement of chemicals and equipments completed and lab started functioning | Idukki QCDL - AE | |
| 27 Jun 2025 | Balance civil work is going on | Kochi QC Dn EE | |
| 22 Oct 2024 | Civil work and procurement of glasswares completed and bill submitted.90% of equipments purchased. Balance purchase going on. | Kochi QC Sub Division - AEE | |
| 01 Jul 2023 | 70% completed | Kochi QC Sub Division - AEE | |
| 08 Jun 2023 | 45% completed | Kochi QC Sub Division - AEE | |
| 18 May 2023 | work in progress | Kochi QC Sub Division - AEE | |
| 11 May 2023 | work in progress | Kochi QC Sub Division - AEE | |
| 05 May 2023 | Work in progress | Kochi QC Sub Division - AEE | |
| 29 Mar 2023 | Work Started | Kochi QC Sub Division - AEE | |
| 14 Mar 2023 | Work awarded | Kochi QC Sub Division - AEE |