| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 04 Oct 2021 | 16% Completed | Kottarakkara PH Dn EE | |
| 16 Aug 2021 | 10% completed | Kottarakkara PH Dn EE | |
| 14 Jul 2021 | 5% completed | Kottarakkara PH Dn EE | |
| 06 Jul 2021 | 5% completed | Kottarakkara PH Dn EE | |
| 21 Jun 2021 | Work Started | Kottarakkara PH Dn EE | |
| 05 May 2021 | Agreement executed | Kottarakkara PH Dn EE | |
| 05 Apr 2021 | Agreement Executed | Kottarakkara PH Dn EE | |
| 23 Mar 2021 | Agreement Executed | Kottarakkara PH Dn EE | |
| 18 Mar 2021 | Agreement Executed | Kottarakkara PH Dn EE | |
| 17 Mar 2021 | Agreement Executed | Kottarakkara PH Dn EE |