| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 25 Jun 2024 | Status of work same since January 2024 | Kadakkal PH Sn - AE | |
| 18 Sep 2022 | 2352/6147 connections provided in various wards. | Kottarakkara PH Dn EE | |
| 01 Jun 2022 | 1120 FHTC completed | Kottarakkara PH Dn EE | |
| 06 Mar 2022 | 955FHTC Completed and pipe laying work is in progress | Kottarakkara PH Dn EE | |
| 28 Feb 2022 | 955FHTC Completed and work is in progress | Kottarakkara PH Dn EE | |
| 04 Feb 2022 | 36%completed | Kottarakkara PH Dn EE | |
| 03 Feb 2022 | 36%completed | Kottarakkara PH Dn EE | |
| 27 Jan 2022 | 980 FHTC Completed. work is in progress | Kottarakkara PH Dn EE | |
| 27 Dec 2021 | 30%completed | Kottarakkara PH Dn EE | |