Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
26 Oct 2023 | 2nd and part bill submitted to DN office on 5/9/2023.Tota PIPE Laid -18173m , Total connection -160nos,51 nos tagged | Ollur AE | |
21 Oct 2023 | 2nd and part bill submitted to DN office on 5/9/2023.Tota PIPE Laid -16809m , Total connection -160nos,51 nos tagged | Ollur AE | |
16 Oct 2023 | 2nd and part bill submitted to DN office on 5/9/2023.Tota PIPE Laid -14701m , Total connection -160nos | Ollur AE | |
10 Oct 2023 | 2nd and part bill submitted to DN office on 5/9/2023.Tota PIPE Laid -14701m , Total connection -160nos | Ollur AE | |
04 Oct 2023 | 2nd and part bill submitted to DN office on 5/9/2023.Tota PIPE Laid -13524m , Total connection -100nos | Ollur AE | |
30 Sep 2023 | 2nd and part bill submitted to DN office on 5/9/2023.Tota PIPE Laid -13524m , Total connection -100nos | Ollur AE | |
25 Sep 2023 | 2nd and part bill submitted to DN office on 5/9/2023.Tota PIPE Layed -11534, Total connection -50nos | Ollur AE | |
19 Sep 2023 | 2nd and part bill submitted to DN office on 5/9/2023.110 mm HDPE=6310 m 75 mm PVC=2078 m 63 mm PVC=540 m 50 mm PVC=156 m Total=9084 m | Ollur AE | |
14 Sep 2023 | 2nd and part bill submitted to DN office on 5/9/2023 | Chalakudy AEE | |
11 Sep 2023 | Work in progress, Total pipe laying-5854m,Total House connection-28Nos | Ollur AE |