15 Dec 2023 2nd and part bill submitted to DN office on 5/9/2023.Total PIPE Laid -26800m, Total connection -160nos,129 nos tagged. Ollur AE
10 Dec 2023 2nd and part bill submitted to DN office on 5/9/2023.Total PIPE Laid -26381m, Total connection -160nos,129 nos tagged Ollur AE
05 Dec 2023 2nd and part bill submitted to DN office on 5/9/2023.Total PIPE Laid -26381m, Total connection -160nos,129 nos tagged Ollur AE
30 Nov 2023 2nd and part bill submitted to DN office on 5/9/2023.Total PIPE Laid -26381m, Total connection -160nos,129 nos tagged Ollur AE
25 Nov 2023 2nd and part bill submitted to DN office on 5/9/2023.Tota PIPE Laid -25933m, Total connection -160nos,129 nos tagged Ollur AE
21 Nov 2023 2nd and part bill submitted to DN office on 5/9/2023.Tota PIPE Laid -25km, Total connection -160nos,129 nos tagged Ollur AE
14 Nov 2023 2nd and part bill submitted to DN office on 5/9/2023.Tota PIPE Laid -20000m , Total connection -160nos,129 nos tagged Ollur AE
09 Nov 2023 2nd and part bill submitted to DN office on 5/9/2023.Tota PIPE Laid -18500m , Total connection -160nos,129 nos tagged Ollur AE
04 Nov 2023 2nd and part bill submitted to DN office on 5/9/2023.Tota PIPE Laid -18500m , Total connection -160nos,129 nos tagged Ollur AE
30 Oct 2023 2nd and part bill submitted to DN office on 5/9/2023.Tota PIPE Laid -18500m , Total connection -160nos,129 nos tagged Ollur AE