Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
15 Dec 2023 | 2nd and part bill submitted to DN office on 5/9/2023.Total PIPE Laid -26800m, Total connection -160nos,129 nos tagged. | Ollur AE | |
10 Dec 2023 | 2nd and part bill submitted to DN office on 5/9/2023.Total PIPE Laid -26381m, Total connection -160nos,129 nos tagged | Ollur AE | |
05 Dec 2023 | 2nd and part bill submitted to DN office on 5/9/2023.Total PIPE Laid -26381m, Total connection -160nos,129 nos tagged | Ollur AE | |
30 Nov 2023 | 2nd and part bill submitted to DN office on 5/9/2023.Total PIPE Laid -26381m, Total connection -160nos,129 nos tagged | Ollur AE | |
25 Nov 2023 | 2nd and part bill submitted to DN office on 5/9/2023.Tota PIPE Laid -25933m, Total connection -160nos,129 nos tagged | Ollur AE | |
21 Nov 2023 | 2nd and part bill submitted to DN office on 5/9/2023.Tota PIPE Laid -25km, Total connection -160nos,129 nos tagged | Ollur AE | |
14 Nov 2023 | 2nd and part bill submitted to DN office on 5/9/2023.Tota PIPE Laid -20000m , Total connection -160nos,129 nos tagged | Ollur AE | |
09 Nov 2023 | 2nd and part bill submitted to DN office on 5/9/2023.Tota PIPE Laid -18500m , Total connection -160nos,129 nos tagged | Ollur AE | |
04 Nov 2023 | 2nd and part bill submitted to DN office on 5/9/2023.Tota PIPE Laid -18500m , Total connection -160nos,129 nos tagged | Ollur AE | |
30 Oct 2023 | 2nd and part bill submitted to DN office on 5/9/2023.Tota PIPE Laid -18500m , Total connection -160nos,129 nos tagged | Ollur AE |