| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 28 Sep 2026 | Work completed, RE submitted | Thalassery PH Sn AE | |
| 08 Jul 2026 | 18.67 km of pipeline laid and FHTC -1300 HTC -8 are given. Interconnection work, GSB & concrete work in progress | Thalassery PH Sn AE | |
| 17 Jun 2026 | 18.67 km of pipeline laid and FHTC -1300 HTC -8 are given. Interconnection work, GSB & concrete work in progress | Thalassery PH Sn AE | |
| 04 Jun 2026 | 18.5986 km of pipeline laid and FHTC -1300 HTC -8 are given. Interconnection work, GSB & concrete work in progress | Thalassery PH Sn AE | |
| 29 Apr 2026 | 18.5986 km of pipeline laid and FHTC -1248 HTC -5 are given. Interconnection work, GSB & concrete work in progress | Thalassery PH Sn AE | |
| 18 Apr 2026 | 18.5986 km of pipeline laid and FHTC -1248 HTC -5 are given. Interconnection work, GSB & concrete work in progress | Thalassery PH Sn AE | |
| 10 Apr 2026 | 18.5986 km of pipeline laid and FHTC -1052 HTC -178 are given. Interconnection work, GSB & concrete work in progress | Thalassery PH Sn AE | |
| 30 Mar 2026 | 18.5986 km of pipeline laid and FHTC -1052 HTC -178 are given. Interconnection work, GSB & concrete work in progress | Thalassery PH Sn AE | |
| 23 Mar 2026 | 18.5986 km of pipeline laid and FHTC -1052 HTC -178 are given. Interconnection work, GSB & concrete work in progress | Thalassery PH Sn AE | |
| 11 Mar 2026 | 18.408 km of pipeline laid and FHTC -1052 HTC -178 are given. Interconnection work, GSB & concrete work in progress | Thalassery PH Sn AE |