Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
07 Apr 2022 | Package 1 - 99 % and package 2- completed | Cherthala PH SUb Dn | |
06 Apr 2022 | Package 1 - 99 % and package 2- completed | Cherthala PH SUb Dn | |
05 Apr 2022 | Package 1 - 99 % and package 2- completed | Cherthala PH SUb Dn | |
04 Apr 2022 | Package 1 - 99 % and package 2- completed | Cherthala PH SUb Dn | |
02 Apr 2022 | Package 1 - 99 % and package 2- completed | Cherthala PH SUb Dn | |
01 Apr 2022 | Package 1 - 99 % and package 2- completed | Cherthala PH SUb Dn | |
31 Mar 2022 | Package 1 - 99 % and package 2- 95 % completed | Cherthala PH SUb Dn | |
30 Mar 2022 | Package 1 - 99 % and package 2- 95 % completed | Cherthala PH SUb Dn | |
26 Mar 2022 | Package 1 - 99 % and package 2- 95 % completed | Cherthala PH SUb Dn | |
25 Mar 2022 | Package 1 - 99 % and package 2- 95 % completed | Cherthala PH SUb Dn |