Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
07 Apr 2022 Package 1 - 99 % and package 2- completed Cherthala PH SUb Dn
06 Apr 2022 Package 1 - 99 % and package 2- completed Cherthala PH SUb Dn
05 Apr 2022 Package 1 - 99 % and package 2- completed Cherthala PH SUb Dn
04 Apr 2022 Package 1 - 99 % and package 2- completed Cherthala PH SUb Dn
02 Apr 2022 Package 1 - 99 % and package 2- completed Cherthala PH SUb Dn
01 Apr 2022 Package 1 - 99 % and package 2- completed Cherthala PH SUb Dn
31 Mar 2022 Package 1 - 99 % and package 2- 95 % completed Cherthala PH SUb Dn
30 Mar 2022 Package 1 - 99 % and package 2- 95 % completed Cherthala PH SUb Dn
26 Mar 2022 Package 1 - 99 % and package 2- 95 % completed Cherthala PH SUb Dn
25 Mar 2022 Package 1 - 99 % and package 2- 95 % completed Cherthala PH SUb Dn