| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 11 Apr 2025 | As per the direction from higher office this estimate split in to four, these works are executed and completed. | Sasthamcotta WS Sn 2 HW - AE | |
| 09 Apr 2025 | Tender cancelled. New estimate submitted for approval. | Sasthamcotta WS Sn 2 HW - AE | |
| 07 Apr 2025 | Tender cancelled. New estimate submitted for approval. | Sasthamcotta WS Sn 2 HW - AE | |
| 04 Apr 2025 | Tender cancelled. New estimate submitted for approval. | Sasthamcotta WS Sn 2 HW - AE | |
| 01 Apr 2025 | Tender cancelled. New estimate submitted for approval. | Sasthamcotta WS Sn 2 HW - AE | |
| 29 Mar 2025 | Tender cancelled. New estimate submitted for approval. | Sasthamcotta WS Sn 2 HW - AE | |
| 26 Mar 2025 | Tender cancelled. New estimate submitted for approval. | Sasthamcotta WS Sn 2 HW - AE | |
| 24 Mar 2025 | Tender cancelled. New estimate submitted for approval. | Sasthamcotta WS Sn 2 HW - AE | |
| 19 Mar 2025 | Tender cancelled. New estimate submitted for approval. | Sasthamcotta WS Sn 2 HW - AE | |
| 13 Mar 2025 | Tender cancelled. New estimate submitted for approval. | Sasthamcotta WS Sn 2 HW - AE |