Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
14 Jun 2024 | Phase 2 - Total - (63 mm PVC ) -8159, 2186FHTC | Pattimattom - Kunnathunadu AE | |
13 Jun 2024 | Phase 2 - Total - (63 mm PVC ) -8159, 2202FHTC | Pattimattom - Kunnathunadu AE | |
11 Jun 2024 | Phase 2 - Total - (63 mm PVC ) -8159, 2202FHTC | Pattimattom - Kunnathunadu AE | |
10 Jun 2024 | Phase 2 - Total - (63 mm PVC ) -8159, 2202FHTC | Pattimattom - Kunnathunadu AE | |
07 Jun 2024 | Phase 2 - Total - (63 mm PVC ) -8159, 2202FHTC | Pattimattom - Kunnathunadu AE | |
06 Jun 2024 | Phase 2 - Total - (63 mm PVC ) -8159, 2202FHTC | Pattimattom - Kunnathunadu AE | |
05 Jun 2024 | Phase 2 - Total - (63 mm PVC ) -8159, 2202FHTC | Pattimattom - Kunnathunadu AE | |
04 Jun 2024 | Phase 2 - Total - (63 mm PVC ) -8159, 2202FHTC | Pattimattom - Kunnathunadu AE | |
03 Jun 2024 | Phase 2 - Total - (63 mm PVC ) -8159, 2202FHTC | Pattimattom - Kunnathunadu AE | |
01 Jun 2024 | Phase 2 - Total - (63 mm PVC ) -8159, 2202FHTC | Pattimattom - Kunnathunadu AE |