Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
09 Jan 2024 | 80mm GI welding ward 9 | Kaduthuruthy Dn EE | |
09 Jan 2024 | No work | Kaduthuruthy Dn EE | |
08 Jan 2024 | 80mm GI laying in ward 8 | Kaduthuruthy Dn EE | |
07 Jan 2024 | 80mm GI laying in ward 8 | Kaduthuruthy Dn EE | |
06 Jan 2024 | 80mm GI laying in ward 8 | Kaduthuruthy Dn EE | |
05 Jan 2024 | 100mm GI laying 80mm GI laying in ward 8 | Kaduthuruthy Dn EE | |
04 Jan 2024 | 100mm GI laying 80mm GI laying in ward 8 | Kaduthuruthy Dn EE | |
03 Jan 2024 | 100mm GI laying 80mm GI laying in ward 8 | Kaduthuruthy Dn EE | |
02 Jan 2024 | 100mm GI laying 80mm GI laying in ward 8 | Kaduthuruthy Dn EE | |
01 Jan 2024 | 100 mm GI laying ward 8 | Kaduthuruthy Dn EE |