Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
29 Jan 2024 | No work | Kaduthuruthy Dn EE | |
28 Jan 2024 | No work | Kaduthuruthy Dn EE | |
27 Jan 2024 | No work | Kaduthuruthy Dn EE | |
26 Jan 2024 | No work | Kaduthuruthy Dn EE | |
25 Jan 2024 | No work | Kaduthuruthy Dn EE | |
24 Jan 2024 | 50 mm GI Interconnection ward 09 | Kaduthuruthy Dn EE | |
23 Jan 2024 | 80 mm GI Interconnection ward 08 | Kaduthuruthy Dn EE | |
22 Jan 2024 | No work | Kaduthuruthy Dn EE | |
21 Jan 2024 | No work | Kaduthuruthy Dn EE | |
20 Jan 2024 | 80mm GM valve fixing | Kaduthuruthy Dn EE |