Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
03 Oct 2023 | 10800m pipe laid. Compound wall work started at poovakala pump house. 420 connections given.Construction pump house started. Road restoration work started | Thiruvalla PH Dn EE | |
06 Mar 2023 | 6500m pipe laid. Compound wall work started at Poovakala pump house.192 connnections | Thiruvalla PH Sub Dn - AEE | |
03 Feb 2023 | 6500m pipe laid. Compound wall work started at Poovakala pump house.29FHTC,60 HTC | Thiruvalla PH Sub Dn - AEE | |
02 Feb 2023 | 6500m pipe laid. Compound wall work started at Poovakala pump house.27FHTC,60 HTC | Thiruvalla PH Sub Dn - AEE | |
31 Jan 2023 | 6500m pipe laid. Compound wall work started at Poovakala pump house.27 FHTC,50 HTC | Thiruvalla PH Sub Dn - AEE | |
19 Jan 2023 | 6000m pipe laid. Compound wall work started at Poovakala pump house.25 FHTC,43 HTC | Thiruvalla PH Sub Dn - AEE | |
17 Jan 2023 | 6000m pipe laid. Compound wall work started at Poovakala pump house.25 FHTC,40 HTC | Thiruvalla PH Sub Dn - AEE | |
12 Jan 2023 | 5400m pipe laid. Compound wall work started at Poovakala pump house.22 FHTC,35 HTC | Thiruvalla PH Sub Dn - AEE | |
09 Jan 2023 | 5300m pipe laid. Compound wall work started at Poovakala pump house.18 FHTC,35 HTC | Thiruvalla PH Sub Dn - AEE | |
23 Nov 2022 | 3000m pipe laid | Thiruvalla PH Sub Dn - AEE |