Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
26 Jan 2022 | Line extension work is going on. 75mm pvc pipe 1550m, 90mm pvc pipe 1100m and 110mm pvc pipe 200 m laying completed | Alappuzha PH Sn AE | |
20 Jan 2022 | Line extension work is going on | Alappuzha PH Sn AE | |
13 Jan 2022 | Line extension work is going on | Alappuzha PH Sn AE | |
04 Jan 2022 | Line extension work is going on | Alappuzha PH Sn AE | |
28 Dec 2021 | Line extension work is going on | Alappuzha PH Sn AE | |
27 Dec 2021 | Line extension work is going on | Alappuzha PH Sn AE | |
23 Dec 2021 | Line extension work is going on | Alappuzha PH Sn AE | |
17 Dec 2021 | 2077/2077 nos FHTC completed | Alappuzha PH Sn AE | |
14 Dec 2021 | Line extension work is going on | Alappuzha PH Sn AE | |
10 Dec 2021 | 2070/2077nos FHTC completed | Alappuzha PH Sn AE |