Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
14 Jun 2021 | 1967/2077 nos FHTC completed | Alappuzha PH Dn EE | |
12 Jun 2021 | 1957/2077 nos FHTC completed | Alappuzha PH Dn EE | |
07 Jun 2021 | 1927/2077 FHTC completed | Alappuzha PH Dn EE | |
05 Jun 2021 | 1927/2077 FHTC completed | Alappuzha PH Dn EE | |
02 Jun 2021 | 1897/2077 FHTC completed. Work resumed | Alappuzha PH Dn EE | |
26 May 2021 | 1897/2077 FHTC completed. No work due to Covid 19 containment zone and Lock down | Alappuzha PH Dn EE | |
17 May 2021 | No work due to Covid 19 Containment Zone and Lock down | Alappuzha PH Dn EE | |
10 May 2021 | 1897/2077 house connections given | Alappuzha PH Dn EE | |
03 May 2021 | 1890/2077 house connections given | Alappuzha PH Dn EE | |
27 Apr 2021 | 1853/2077 house connections given | Alappuzha PH Dn EE |