06 Jun 2024 13 LL AMBALAVAYAL OHSR SIDE WALL CONCRETE RE SHUTTERING Sulthan Bathery PH Sn - AE
04 Jun 2024 13 LL OHSR AMBALAVAYAL SIDE WALL CONCRTE COMPLETED Sulthan Bathery PH Sn - AE
01 Jun 2024 13 LL ohsr main side wall concrete on going Sulthan Bathery PH Sn - AE
28 May 2024 13 LL Ambalavayal ohsr hunch concrete work completed Sulthan Bathery PH Sn - AE
20 May 2024 13 LL Ambalavayal ohsr hunch concrete on going Sulthan Bathery PH Sn - AE
30 Apr 2024 AMBALAVAYAL 13 LL OHSR MAIN SLAB CONCRETE WORK COMPLETED Sulthan Bathery PH Sn - AE
29 Apr 2024 AMBALAVAYAL 13 LL OHSR MAIN SLAB CONCRETE WORK IS PROGRESED Sulthan Bathery PH Sn - AE
29 Apr 2024 13 LL OHSR MAIN SLAB CONCRETE WORK ON GOING Sulthan Bathery PH Sn - AE
25 Apr 2024 Ambalavayal 13LL GLSR , main base slab shuttering works completed , reinforcement works progress .... Sulthan Bathery PH Sn - AE
11 Apr 2024 Total pipe laid 58.24 Km, 13LL Ambalavayal OHSR , Base Slab Shuttering and Reinforcement works progress , Column and beam works completed up to base level Sulthan Bathery PH Sn - AE