| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 22 May 2025 | Package I and II- Distribution pipeline works are ongoing. | Kattappana AEE 1 | |
| 19 May 2025 | Package I and II- Distribution pipeline works are ongoing. | Kattappana AEE 1 | |
| 16 May 2025 | Package I and II- Distribution pipeline works are ongoing. | Kattappana AEE 1 | |
| 13 May 2025 | Package I and II- Distribution pipeline works are ongoing. | Kattappana AEE 1 | |
| 10 May 2025 | Package I and II- Distribution pipeline works are ongoing. | Kattappana AEE 1 | |
| 07 May 2025 | Package I and II- Distribution pipeline works are ongoing. | Kattappana AEE 1 | |
| 04 May 2025 | Package I and II- Distribution pipeline works are ongoing. | Kattappana AEE 1 | |
| 01 May 2025 | Package I and II- Distribution pipeline works are ongoing. | Kattappana AEE 1 | |
| 01 May 2025 | So far, 3,100 metres of 110 mm PVC pipeline have been laid out of 3,500 metres, and 24 metres of 100 mm GI pipeline have been laid out of 480 metres. In total, 3,124 metres of distribution pipeline have been laid out of 3,980 metres. | Kattappana AEE 1 | |
| 28 Apr 2025 | Package I and II- Distribution pipeline works are ongoing. | Kattappana AEE 1 |