| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 21 Jun 2025 | Package I and II- No work | Kattappana AEE 1 | |
| 18 Jun 2025 | Package I and II- No work | Kattappana AEE 1 | |
| 15 Jun 2025 | Package I and II- No work | Kattappana AEE 1 | |
| 12 Jun 2025 | Package I and II- No work | Kattappana AEE 1 | |
| 09 Jun 2025 | Package I and II- No work | Kattappana AEE 1 | |
| 06 Jun 2025 | Package I and II- No work | Kattappana AEE 1 | |
| 03 Jun 2025 | Pipeline works of Packages I and II were halted due to rain. | Kattappana AEE 1 | |
| 31 May 2025 | Pipeline works of Packages I and II were halted due to rain. | Kattappana AEE 1 | |
| 28 May 2025 | Pipeline works of Packages I and II were halted due to rain. | Kattappana AEE 1 | |
| 25 May 2025 | Pipeline works for Packages I and II were halted due to rain. | Kattappana AEE 1 |