| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 03 Jun 2023 | Issued TS on 04/05/2023 ,WRD/KWA-CE(CR)/EST_TS/7374/2022_26_1_1 Dated: 04-05-2023 | Kattappana AEE 1 | |
| 02 Jun 2023 | TS Sanctioned on 04/05/2023 ,WRD/KWA-CE(CR)/EST_TS/7374/2022_26_1_1 Dated: 04-05-2023 | Kattappana AEE 1 | |
| 01 Jun 2023 | TS Sanctioned on 04/05/2023 ,WRD/KWA-CE(CR)/EST_TS/7374/2022_26_1_1 Dated: 04-05-2023 | Kattappana AEE 1 | |
| 06 May 2023 | TS Sanctioned on 04/05/2023 ,WRD/KWA-CE(CR)/EST_TS/7374/2022_26_1_1 Dated: 04-05-2023 | Kattappana AEE 1 | |
| 03 Jun 2023 | Estimate preperation and sanction stage. | Kattappana AEE 1 | |
| 01 Jun 2023 | Estimate preperation and sanction stage. | Kattapana AE 1 | |
| 29 May 2023 | Estimate preperation and sanction stage. | Kattapana AE 1 | |
| 24 May 2023 | Estimate preperation and sanction stage. | Kattapana AE 1 | |
| 21 Jan 2023 | Estimate preperation and sanction stage. | Kattapana AE 1 |